Qi family classroom: the order of the main materials to enter the venue

It is very important for home decoration and making good advances. If you think of a complete plan, will it be clear when you are doing renovations, save time and worry? From another perspective, time is money!


壹 Floor solid wood floor Minor sofa

1. Designers, owners, and constructors approach the bottom of the trade, and plumbers line up and open the trunking. During the electrician's opening of the trunking, the owner needs to contact the cabinet company to confirm the location of the cabinets and start ordering cookers and fumes. Machines, water heaters, pans, squatting pans, toilets, washbasins, floor drains, power boxes;

2. After completion of the trunking trough of the hydroelectrician (generally, the time for opening the trough is 2-3 days), the water and electricity lines will begin to be installed. The owner will start to order wall and floor tiles (the quantity reference decoration quotation can also be provided by the merchant). Pull the squatting pan to the site.

3. After the completion of the hydropower (typical hydropower installation time is one week), after the completion of the hydropower, the masonry approaching base will be reconstructed. At this time, the owner needs to pull the tiles to the site and schedule the Door and door cover (mainly to make the door to the site Production door size);

4. When the mason enters the site, the construction party can arrange the woodwork to enter the ground and start the ceiling construction or other carpentry production projects at the same time depending on the site conditions; (The owner needs to contact the professional drilling to open the air conditioning hole and the water heater exhaust hole).

5. After the completion of the carpentry and masonry tiling works, waterproof works, etc., if the bathroom needs to be partitioned or shower room, the owner can inform them of the size of the arrivals and start production; the construction party will arrange the painter to enter the field. If the painter enters the market, if you choose to paste the wallpaper, you can start to schedule the wallpaper at this time (because the wallpaper is generally delivered from the field and there is no regular period of about 10 days).

6. After the painter's wall putty is scraped, the owner buys the aluminum buckle plate, bathroom heater, kitchen ceiling lamp, exhaust fan, and informs the kitchen three-piece pulls to the construction site (stove, cooker fume, water heater) and informs them of the door-to-door installation.

7. After the painter finishes the first pass of the primer, the owner needs to inform the installation of the door and door cover (the owner needs to purchase the hardware when installing the door. For example: lock, hinge, handle, etc.) If the kitchen or bathroom is slippery The door, then after the door cover is installed, it needs to make the sliding door size and start the production.

8. After the door is installed, the owner will need to start choosing the color of the wall paint.

9. After the door is installed, the painter starts painting the latex paint after the base layer has been completely processed and dried (if it is full-wall paper, the painter is informed to do the wallpaper basic layer processing). During the painting (or during the wallpapering), the owner needs Begin to purchase wood floors, lamps, curtains, pendants, sanitary ware, and switch panels.

10. After the painter is finished, the owner needs to install lighting fixtures, pendants, fixtures, sanitary ware, and switch panels to the site.

11. After the fixtures and sanitary ware are installed, the owner informs the wooden floor to enter the site for installation. After the wooden floor is installed, the land will be cleared and cleaned. After the cleaning is completed, the owner can notify the curtains and Furniture to enter the site.

Renovation process Three trees Paint Lacquer Switch windows Latex paint Toilet partitions Fabric sofa Doors Kitchen cabinets Partition cabinets Floor tiles Kitchen doors Doors Doors Doors for bathroom Doors for bathroom Sizes for bathroom Bathroom partitions Bathroom ceilings Bathroom exhaust fans Bathroom design Bathrooms Waterproof toilets Brick